Updates
News

Pumping-mode tests for Dniester PSPP unit No. 4
On 9 November 2021, unit No. 4 “Anna” at the Dniester Pumped Storage Power Plant underwent pumping-mode tests.

START-UP OF HYDRAULIC UNIT No.4 OF DNIESTER PSPP IN GENERATOR MODE
Hydroelectric unit No. 4 Dniester PSPP (Ukrhydroenergo PJSC), was launched in the generator mode (capacity is 324 MW). This event is a great importance for the United Energy System of Ukraine, as new shunting capacities have been added. The general contractor for the construction of the Dniester PSPP is the Consortium RPA Ukrgidroenergobud.

Dniester PSPP unit No. 4 generates its first 200,000 kWh of electricity
Unit No. 4 at Ukrhydroenergo’s Dniester Pumped Storage Power Plant generated its first 200,000 kWh of electricity.

MIDDLE DNIPROVSKA HPP RECEIVES NEW MODERN TRANSFORMER
As part of the reconstruction of the second stage at the Middle Dnieper HPP of PJSC Ukrhydroenergo a new transformer of own needs T-5 was put under voltage for testing. The works were performed by the Consortium RPA Ukrgidroenergobud.

WORKS ON REPLACEMENT OF BLOCK TRANSFORMERS
As part of the replacement of block power transformers 70,000 kVA (T1, T2) branch Kakhovka Neporozhny HPP PJSC Ukrhydroenergo, Consortium RPA Ukrgidroenergobud dismantled the T2 transformer (70,000 kVA).

TRANSFORMER T-4 IS SUPPLIED AT OPERATING VOLTAGE AT DNIESTER PSPP
At the Dniester PSPP of PJSC Ukrhydroenergo, a T-4 transformer has been put under operating voltage as part of the construction of the second stage of the largest pump storage power plant in Europe. The general contractor for the construction of the Dniester PSPP is the Consortium RPA Ukrgidroenergobud.

COMMISSIONING WORKS ON THE HYDRAULIC UNIT №4 DNIESTER PSPP
At the Dniester PSPP PJSC "Ukrhydroenergo" continue commissioning works on the hydraulic unit №4. The general contractor of the construction is the Consortium RPA Ukrgidroenergobud.

DNIESTER PSPP: KEY MOMENTS BEFORE THE START-UP OF THE FOURTH HYDRAULIC UNIT HAVE BEEN DETERMINED
A traditional meeting was held at the Dniester PSPP, which addressed topical issues of construction of the fourth hydro unit and its preparation for commissioning. After a detailed analysis of the status of the works by a joint decision with the heads of subcontractors involved in the construction, it was determined which works should be completed on the hydraulic unit № 4 of the Dniester PSPP.

CONSTRUCTION OF THE SECOND STAGE OF THE DNIESTER PSPP CONTINUES
On May 28, was held a meeting which traditionally brought together the management of PJSC Ukrhydroenergo, the Consortium RPA Ukrgidroenergobud, and all subcontractors involved in the construction of the most ambitious energy project in modern Ukraine.