Dnipro-1 Hydroelectric Power Plant

Repair of concrete water-conduit surfaces and the spillway dam crossing.

Type
Infrastructure
Status
Completed
Years
2017–2019
Location
Ukraine
Role
Repair works

Project gallery

In 2017, repair of the concrete surfaces of the water conduits of hydro units No. 13, 15 and 18. In 2019, repair of the road crossing over the spillway dam with restoration of the asphalt-concrete surface and partial repair of expansion joints.

Scope of works

  • concrete surface repair
  • crossing repair with asphalt surface