Kakhovka Hydroelectric Power Plant

Supply and installation of new repair shutters and spillway dam gates.

Type
Equipment
Status
Completed
Years
2019–2019
Location
Ukraine
Role
Supply & installation

Project gallery

In 2019, purchase and delivery of new repair shutters for the afterbay suction pipes (3 pcs.); purchase, delivery and installation of flat wheel gates for the spillway dam (3 pcs.) with reconstruction of carts and hooks (2 sets) and the supply and installation of a flat shutter.

Scope of works

  • suction pipe repair shutters
  • spillway flat gates
  • cart & hook reconstruction