Tashlyk Pumped Storage Power Plant

Commissioning works that put stage I into operation — two 150 MW hydro units.

Type
PSPP
Status
Completed
Years
2006–2007
Location
Ukraine
Role
Commissioning works

Project gallery

In 2006–2007, a complex of commissioning works that ensured the commissioning of stage I of the Tashlyk PSPP, consisting of two hydro units with a capacity of 150 MW each.

Scope of works

  • commissioning works
  • start-up of two 150 MW hydro units